EV Solutions has been appointed to manage the installation of an infrastructure capable of supporting 150 EV charge points. The project is ongoing and, to date, a consultation of the leaseholders established the following.
- Leaseholders would like the ability to choose their own charge points
- The system should be “future-proofed” to enable the use of more powerful chargers in the future
EV Solutions has established likely power needs over the next few years, and we are currently working on a design to enable the upgrade of a transformer and accompanying cabinets to supply the anticipated power needs.
A contribution from each of the leaseholders with car parking spaces has been agreed and a grant application has been submitted to OZEV.
The finished system is planned to incorporate a billing system, load balancing to keep infrastructure costs to a minimum and service and support beyond the initial installation.